The Hidden Cost of Waiting to Plan Your ERCES System

Most construction teams do not think about emergency responder radio coverage until someone asks about it, usually late, usually right before an inspection. By then, the easy decisions are gone.

An Emergency Responder Communication Enhancement System, or ERCES, is the infrastructure that lets firefighters, police, and EMS communicate on their radios once they walk inside a building. It sounds like a narrow technical requirement, but it behaves more like a structural decision. Where the equipment room sits, how cabling routes between floors, where battery backup lives, all of it needs to be worked out while the building is still on paper. Once walls are framed and ceilings are closed, the same decisions cost more, take longer, and sometimes are not even possible without tearing something open.

Why timing changes everything

Early in a project, almost nothing about ERCES is fixed. There is room to choose where the donor antenna goes, how the signal reaches interior spaces, and how the system ties into the building’s electrical and fire alarm infrastructure without competing with other trades for the same chase or riser. The building is still flexible enough to absorb the requirement without friction.

That flexibility disappears fast. Once framing, drywall, and ceiling grids are in, adding a system that was never part of the plan means opening finished spaces, rerouting conduit around structure that already exists, and coordinating with trades who have already moved past that phase of the project. It is not just more expensive. It is slower, and on a construction schedule, slow has its own cost.

This is a large part of why the Safer Buildings Coalition, the nonprofit organization focused on in-building public safety communications, treats ERCES with the same seriousness as fire alarms and sprinkler systems rather than as an optional add on. Their public safety primer makes the case that these systems are life safety infrastructure, not a specialty feature, and that framing matters for when planning should start. A fire suppression system is never an afterthought in a building’s design. ERCES increasingly cannot be either, because most modern building codes require it, and Authorities Having Jurisdiction are paying closer attention to how and when it gets addressed.

What gets harder when planning starts late

Space for equipment and batteries. ERCES requires a dedicated equipment room with backup power, typically batteries sized to keep the system running for at least 24 hours without external power. Finding that space is simple during design. Finding it after mechanical, electrical, and plumbing rooms are already laid out is not.

Coordination with the fire alarm system. Code requires ERCES to report system status and faults through the building’s fire alarm system. That connection is straightforward when the fire alarm contractor and the ERCES designer are working from the same set of drawings from the start. It becomes a back and forth of change orders when one system is already installed and the other is trying to catch up.

Pathway and cabling routes. Antenna cabling has to travel through the building without interfering with other systems and without excessive signal loss over distance. Early design allows that routing to happen cleanly. Late in construction, the available paths are whatever is left over, which is rarely the most efficient option.

AHJ expectations. Every jurisdiction interprets code requirements a little differently, and getting in front of the local Authority Having Jurisdiction early gives a project team a clear picture of what will actually be required at final inspection. Discovering those expectations for the first time during a failed test is the outcome nobody wants, and it is also the most common way ERCES ends up holding up a certificate of occupancy.

None of this is unique to any one building type. Distribution centers, Senior Living communities, retail locations, schools, and hospitality properties all face the same underlying dynamic. The building materials that make modern construction more energy efficient, steel framing, low emissivity glass, dense insulation, are the same materials that block the radio signals first responders depend on. That tradeoff is built into most new construction now, which is exactly why it needs to be part of the plan from day one rather than a problem discovered later.

Making it part of the process, not a separate project

The building teams who avoid the late stage scramble tend to do one thing consistently: they bring ERCES into the conversation at the same point they bring in fire protection and low voltage design, early enough that it is just one more coordinated system rather than a late addition competing for space and schedule.

That is the kind of planning conversation AWC has with building and facility teams before ground is even broken, working through equipment room location, backup power needs, and how a system will tie into fire alarm and electrical infrastructure while those decisions are still easy to make.

Emergency responder communication requirements are not going away, and enforcement around them is only getting more consistent across jurisdictions. The building projects that treat ERCES as part of the original design, rather than a compliance item to solve later, are the ones that move through inspection and occupancy without the surprises. Whether your project is still early enough to plan for it, or already deep into construction and working through it as a late addition, AWC’s team is available to talk through what your building will need to keep things moving.